Route 46 Corridor Improvements (Whitley 1) |
Description: Near Paso Robles on Route 46 from west of Geneseo Road to east of Almond Drive. Convert to a 4-lane expressway.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo |
City | |
Zip Code | 93446 |
Senate District |
15 |
Assembly District | 33 |
Congressional District | 22 |
Caltrans District |
05 |
County/State Route | San Luis Obispo 46 |
Postmile Begin/End | 36.6 41.2 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 2425 | 2329 |
Lane Miles Added (Mixed) | 9.2 | |
Peak Period Time Savings (minutes) | 164164 | 157673 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | John Luchetta | (805) 549-3175 | john.luchetta@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | John Luchetta | (805) 549-3175 | john.luchetta@dot.ca.gov | |
Right of Way Phase |
Caltrans | John Luchetta | (805) 549-3175 | john.luchetta@dot.ca.gov | |
Construction Phase |
Caltrans | David Rasmussen | (805) 549-3677 | david.rasmussen@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Claudia Espino | (805) 549-3640 | claudia.espino@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $691 | $691 | ||||
IIP Augmentation |
$0 | $613 | $613 | ||||
CMIA |
$67,742 | $-17,964 | $49,778 | ||||
Non-bond Funding | |||||||
State/Federal* |
$33,058 | $-8,018 | $25,040 | ||||
Local** |
$4,200 | $-1,268 | $2,932 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $105,000 | $-25,946 | $79,054 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $0 | $0 | $1,693 | |||
Design(PS&E) |
$7,000 | $-600 | $6,400 | $6,113 | |||
Right of Way |
$11,000 | $600 | $11,600 | $10,981 | |||
Construction |
$87,000 | $-25,946 | $61,054 | $60,185 | |||
Total* | $105,000 | $-25,946 | $79,054 | $78,971 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/01/1998 05/01/2006 |
|
01/01/1998 05/01/2006 |
100 | 01/01/1998 05/19/2006 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2006 02/01/2010 |
|
09/01/2006 02/01/2010 |
100 | 11/01/2006 12/15/2009 |
-2 2 |
|
Begin Right of Way Phase
End Right of Way Phase |
03/01/2007 10/01/2009 |
|
03/01/2007 10/01/2009 |
100 | 03/21/2007 01/06/2009 |
-1 9 |
|
Begin Construction Phase
End Construction Phase |
07/01/2010 07/01/2013 |
|
08/01/2010 08/01/2013 |
100 | 10/25/2010 10/13/2014 |
-3 -15 |
|
Begin Closeout Phase
End Closeout Phase |
08/01/2013 05/01/2014 |
|
09/01/2013 10/01/2014 |
50 | 10/13/2014 07/05/2022 |
-14 -94 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 07/01/2009 | 07/01/2009 | 0 | 0 | |||
Implementation Date | 08/01/2009 | 08/01/2009 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 2425 | 2329 |
Lane Miles Added (Mixed) | 9.2 | |
Peak Period Time Savings (minutes) | 164164 | 157673 |
Bond Funding Cost | |
---|---|
Adopted: |
$67,742,000 |
Current Approved: |
$49,778,000 |
Actual Expenditures: |
$48,130,000 |
Status as of December 31, 2023.